Aurora A27 · Compass
o9 Capability Mapping Blueprint
✦ A Compass for the Programme

Aurora A27 — o9 Capability Mapping Blueprint

Silver → Platinum-Plated Transition | Out-of-the-Box vs. Extension scoring against the o9 Digital Brain (HERO programme)

This blueprint maps the 12 Aurora A27 requirements (Requirements Spec. Register v1.2, owner: Aurora GOPT / Jan Karreby) against Pandora's existing planning system landscape, with depth on the o9 Digital Brain. Each requirement is scored on how much is delivered natively (out-of-the-box) versus how much requires configuration, modelling, or build extensions — and where the work lands across the wider landscape (Logility, Aptean, IPPL/IPPL-120, AX12 MANU, D&A, Merch/O2C).

Scoring Scale · OOTB Fit
90–100%
Native OOTB
Standard o9 capability; configuration only.
70–89%
Mostly OOTB
Core capability native; light modelling/config.
50–69%
OOTB + Extension
Strong base; meaningful config/custom logic or measures.
30–49%
Significant Extension
Native frame, but core logic must be built (rules/integration).
0–29%
External / Integration
Largely owned outside o9 or new integration build.
Constellation

The Pandora planning landscape

Seven systems surround the o9 Digital Brain. Each has a specific role in how Aurora moves from Silver to Platinum-Plated.

o9DIGITAL BRAINLogility(Aptean)ApteanReplenIPPL120AX12MANUD&AAnalyticsMerch/ O2C
Planning System

o9 Digital Brain

Core IBP / demand + supply planning engine for o9 markets. Enterprise Knowledge Graph (EKG) digital twin. Primary mapping target.

Hero Visualization

The OOTB compass

Twelve spokes, twelve requirements. Spoke length is the share o9 delivers natively; outer arc colour signals the GOPT impact. Click any spoke to dive in below.

REQ-0185%REQ-0280%REQ-0345%REQ-0475%REQ-0560%REQ-0670%REQ-0778%REQ-0835%REQ-0972%REQ-1025%REQ-1155%REQ-1258%62%PORTFOLIO OOTBAURORA A27 · 12 REQUIREMENTSSPOKE LENGTH = OOTB FIT · OUTER ARC = GOPT IMPACT
Strongest fit
REQ-01 · 85%

Native data model; the only true build is Aurora-specific DQ gating + the Silver↔PP link governance.

Lowest fit
REQ-10 · 25%

Lowest OOTB fit — o9 consumes natively, but the requirement is fundamentally an external dependency + integration on AX12 MANU.

Portfolio verdict
62% average OOTB

o9 covers the planning spine natively; extensions concentrate on Aurora transition mechanics, retail-grain disaggregation, compliance workflow, and the AX12 integration.

All twelve, in detail

Requirements heatmap

Filter by band or GOPT impact. Click a card to open the full capability mapping on the right.

REQ-01 · Primary: o9 (master) + AX12/PIM upstream

Master Data, Variants & Assortments

Mostly OOTB · 85% OOTBGOPT · Both
Capability Compositionweighted by detail depth
Out-of-the-Box · 31%Configuration · 25%Extension / Build · 23%External / Integration · 21%
Out-of-the-Box

o9 EKG natively models product master, planning attributes, hierarchies and assortments as a digital twin. Variant relationships and attribute-based product structures are first-class. Predecessor–successor (Silver→PP) linkage is a standard lifecycle construct.

Configuration

Configure A27 PP DV attribute set, hierarchy/assortment nodes, and the Silver↔PP link relationship; default-inheritance-from-Silver rule via attribute defaulting; route/BOM planning attributes for hybrid flow.

Extension / Build

Custom validation measures to enforce 'unique ID + valid planning attributes' and 'mandatory Silver↔PP link on Base Transition DVs' as gating data-quality rules with reject reporting (AC3).

External / Integration

Authoritative product/BOM master originates upstream (PIM / AX12); o9 consumes via integration. Load-success confirmation handshakes to downstream systems (Logility, Aptean, IPPL).

Verdict

Native data model; the only true build is Aurora-specific DQ gating + the Silver↔PP link governance.

Deliberately distributed
REQ-03 · Transition Rule Management

The substitution engine exists; the Aurora cutover rule-set is bespoke and ownership is deliberately distributed off GOPT.

External-heavy
REQ-10 · Hybrid Manufacturing Planning

Lowest OOTB fit — o9 consumes natively, but the requirement is fundamentally an external dependency + integration on AX12 MANU.

Workflow-heavy
REQ-08 · Composition & Compliance

Attributes fit o9 but compliance sign-off & COO route logic are workflow-heavy and largely external — low OOTB.

Where the build lands
18 extension items

Concentrated on Aurora transition mechanics, retail-grain disaggregation, compliance workflow, and the AX12 integration.

Where build / integration is required

Extension backlog

Beyond o9 OOTB: every item that must be built, configured, or integrated. Grouped by priority, tagged by owning system and type.

Critical
1
REQ-10Integration

AX12 MANU → o9 integration

Ingest allocation proportions + step lead times; PP setup confirmation; one-cycle change propagation; consistency check

Owner · AX12 MANU → o9 / IPPL-120
High
10
REQ-03Build+Config

Hard/Soft cutover rule engine

Cutover-type config, soft-cutover transfer profiles, override matrix + audit, post-cutover Silver thresholds

Owner · o9 (consumes); Merch/IPPL/Aptean own scope
REQ-03External

Silver disposition / markdown

Disposal/markdown rule for outgoing Silver stock

Owner · Merch / O2C
REQ-05Build

SKU×Store disaggregation

Retail-grain disaggregation with reconciliation; new build below core planning grain

Owner · o9
REQ-05Integration

Aptean replenishment feed

Versioned SKU×Store handoff consumable by Aptean; cadence contract

Owner · o9 → Aptean
REQ-05Build

Wave-2 NPI auto-disaggregation

Scalable automated NPI method to replace Year-1 manual workaround before 2027 (330+ DVs)

Owner · o9
REQ-06Config+Build

Plating finite-capacity model

Weekly finite plating capacity, wave-allocation & capacity-sharing rules, utilisation alerts

Owner · o9 / IPPL-120
REQ-08External+Build

Compliance sign-off workflow

Per-market sign-off gating prior to ship/readiness; COO route logic for hybrid route

Owner · PLM/Compliance + o9 status
REQ-11Build

Silver/PP coexistence alerting

Run-down/build-up deviation alert engine; Silver-vs-PP split views linkable

Owner · o9
REQ-11Integration

CM & in-transit traceability feeds

WIP at platers + in-transit + store-level visibility feeds

Owner · Execution/ERP → o9
REQ-12Build

Unified transition scorecard

Cross-market KPI calc rules, RAG/exception, weekly cadence reconciling demand↔supply/inventory

Owner · o9 IBP
Med
7
REQ-01Build

DQ gating & Silver↔PP link governance

Validation measures enforcing unique ID, valid attributes, mandatory link on Base Transition DVs; reject reporting

Owner · o9
REQ-02Build

Sell-in pack lifecycle logic

Pack-aware phase-in/out (volume, timing, pack composition) for initial Aurora launches

Owner · o9
REQ-04Build

Price-elasticity & pack forecast

Elasticity effect at differing Silver/PP price points + sell-in pack forecast logic

Owner · o9
REQ-07Config

Time-phased insourcing sourcing

Source-mix evolution toward fully insourced model over horizon

Owner · o9 / IPPL-120
REQ-09Integration

Cross-system node-ID MDM

Consistent node IDs across o9 / Logility / IPPL for plater nodes & route legs

Owner · MDM / Integration
REQ-12Build

Value-based KPI views

Revenue / margin-impact views alongside volume KPIs

Owner · o9 IBP / D&A
REQ-12Integration

Non-o9 markets via Logility

Integrate Logility outputs + surface through D&A semantic layer

Owner · Logility / D&A
Where build lands in time

Extension delivery roadmap

Eighteen extension items, three phases, four parallel squads, ten 2-week sprints. Critical path runs through AX12 MANU (REQ-10) and PLM compliance sign-off (REQ-08).

P0 · Foundation
Jul–Sep 2026

MVP Foundation

Data spine + critical integration

Items
4
Story pts
53
Elapsed
~5 sprints / 10 wks
Exit gate

AX12→o9 feed live; master data & node IDs stable; DQ gating passing.

P1 · Transition
Sep–Dec 2026

MVP Transition

Go-live transition mechanics

Items
7
Story pts
76
Elapsed
~5 sprints / 10 wks
Exit gate

Cutover rules, SKU×Store + Aptean feed, capacity model, compliance gating validated for H2-26 launch.

P2 · Follow-on
Jan–Jun 2027

Follow-on Scale

Scorecard, value, Wave-2 scale

Items
7
Story pts
81
Elapsed
~5 sprints / 10 wks
Exit gate

Transition scorecard + value KPIs live; Wave-2 NPI automation ready before 330+ DV wave.

Total18items
210story points
~15 sprints / ~12 months elapsed with parallel squads (vs 48 sprints if serial)
Q3 2026
Q4 2026
Q1 2027
Q2 2027
H2 2027
Squad / Item
S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
Data & Integration5
Demand6
Supply3
Reporting4
Gates
G0
G1
G2
Parallel work

Squad load by sprint

Items in flight · max 3
Data & Integration
2
3
2
1
1
1
1
1
1
1
Demand
2
3
3
2
1
2
Supply
1
2
2
1
1
1
Reporting
1
1
1
3
★ Critical path

AX12 MANU→o9 integration (REQ-10, 5 sprints) and PLM compliance sign-off (REQ-08, 4 sprints) are the longest, externally-dependent items. Start both at sprint 1 / earliest; slippage here moves go-live.

Assumptions

Parallel squads (Data & Integration, Demand, Supply, Reporting); external partners (AX12/Pl2Pr, PLM, Aptean, Logility) resourced to agreed cadence; o9 reference-model alignment maintained to limit custom build.

end P0, ~Sep 2026
Gate G0

Go/No-Go for transition build: AX12 feed flowing, master data + node IDs stable, DQ gating green. Blocks P1 if not met.

end P1, ~Dec 2026
Gate G1

Go-live readiness for H2-2026 launch: cutover rules, SKU×Store + Aptean feed, plating capacity, compliance gating all UAT-signed.

end P2, ~Jun 2027
Gate G2

Wave-2 scale readiness: scorecard + value KPIs live, NPI auto-disaggregation proven before the 330+ DV 2027 wave.

P0 · FoundationP1 · TransitionP2 · Follow-on Critical path1 sprint = 2 weeks · click any bar to open the requirement
Cross-system ownership

Requirement ↔ system dependencies

Each requirement traced to the systems that must deliver against it. Hover to isolate a thread.

REQ-01Master Data, Variants & Assort…REQ-02Lifecycle & Transition PlanningREQ-03Transition Rule ManagementREQ-04Transition & NPI ForecastingREQ-05Forecast Transfer & Disaggrega…REQ-06Capacity Constraint PlanningREQ-07Multi-Source Supply PlanningREQ-08Composition & ComplianceREQ-09Dynamic Supply Network Managem…REQ-10Hybrid Manufacturing PlanningREQ-11Inventory Visibility & Traceab…REQ-12Planning Data Integration & Re…o9IPPL-120AX12 MANUApteanLogilityMerch / O2CD&APLM / MDMExecutionREQUIREMENTSOWNING SYSTEMS

Hover a requirement or system to isolate its dependencies. Derived from primary + extension owner mappings.